Total Movements, member to the Worldwide Project Consortium (WWPC) in India, successfully executed the door-to-port movement of about 2200CBM of Klin Shells from the supplier’s factory to the designated load port in Southern India with the final destination at a Steel Plant project in the Persian Gulf.
A company spokesperson explained: “Our scope included the entire logistics chain, from picking-up of cargo from the supplier's works, loading the Shells onto the hydraulic axles and transportation up to the designated load port covering a distance of about 800Kms.

Key highlights of this execution:
- Large Cargo Dimensions - a substantial diameter of 7 meters
- Enroute Civil Works to facilitate smooth passage of the cargo
- Multi-State Transportation covering a distance of about 800km
- HT/LT line shutdowns were implemented at key points along the route to accommodate the cargo height
- Presence of thick tree cover all along the route
This operation highlights Total Movements' expertise in handling dimension-critical cargo and our ability to execute complex logistics solutions across challenging terrains and long distances.”