Relocating a 192.5 ton steel building frame whole for San Francisco revitalization project

The building frame was jacked up about 18 centimeters (7 inches) and then rolled 37 meters (120 ft.) using 16 Holland Dollies for the structure, six dollies for bracing and two excavators provided by Silverado Contractors, Inc. Once the pier renovations are complete, the building will be rolled back into position about 3 meters (10 feet) higher, where the frame will become a decorative centerpiece for the new neighborhood. The renovated Pier 70 Waterfront Site will feature new affordable housing, waterfront parks, space for artists and local manufacturing, and rehabilitated historic buildings.
Mammoet has the experience and heavy lifting and transport equipment necessary to carefully relocate whole buildings and structures that may lie in the path of new developments. In one such case, Unilever’s new headquarters was successfully placed on top of the existing factory, without impacting operations below.