Conveyor Logistics Ltd, member to the Worldwide Project Consortium (WWPC) for Bangladesh, was employed to receive several outsized components at Ports of Entry, being Mongla and Chittagong.
The experts from Conveyor arranged for the inland transportation by road and river and the delivery to the project site at Ghorasal 365 MW Combined Cycle Power Plant. The heavy-lift items, especially the GAS Turbine (GT) weighing 314 Tons and the Gas Turbine Generator (GTG) weighing 328 Tons, were received from ocean vessels at Mongla Port, loaded onto flat barges and transported on the river from Mongla to Ghorasal.
After discharge from the barges these items got diverted to the project site by manual skidding.