C.H. Robinson Project Logistics recently assisted a customer with transporting 33 large wind turbines from a distribution yard in Garden City, Kansas, to a new windfarm located near Kintyre, North Dakota. Their expert wind team worked tirelessly to organise the 680mi (1,100km) journey which required over 260 truckloads utilising 56 specialised trailers.
7 of the 33 wind turbines, including 3 blades, 3 tower sections, 1 machine head and 1 hub, were delivered as quickly as possible, with the additional 26 turbines delivered later. The project totalled 74,408cbm (6,531.2mtn) of cargo with the largest piece transported being the blade which measured a huge 50.20 x 2.92 x 3.64m.
More than 50 private police escorts were required to transport the OOG cargo (as per various state permit regulations) with 2 of C.H. Robinson's experienced project logistics experts, acting as an extension of their customer's team, present onsite to manage and oversee the aggressive delivery schedule to ensure the success of this enormous project.
Follow us on social media: