BNSF Logistics, member to the Worldwide Project Consortium (WWPC) for the USA, handled the safe and demanding transportation of 3 transformers, each with a weight of 470,000 lbs (213,2 tons) and the size of 25’7 x 11’5 x 14’ (7,83m x 3,51m x 4,27m).
The BNSFL office in Banning, California, managed the transportation, starting from Baltimore until delivery to a substation in Dundalk, Maryland. The scope of work for the BNSFL experts and engineers included road transport to the jobsite , jack & slid and then up-righted onto the foundation, with the height of each unit being 7,83 m.
Follow us on social media: