- Picking up of the anchors from production places including tests and lifting operations utilizing Enerpac Gantry SBL1100
- Trucking to the ro-ro berth on own SPMT
- Ro-Ro loading on to Beluga owned barges and sea transportation to the working area of the Kola Bay
- Anchor lines assembling and installation on the seabottom
- Lowering of the anchors upto 155 mtrs carried out by Enerpac Strand Jacks.
Beluga Projects Logistics builts Murmansk oil terminal
Nov 27, 2017
Beluga Projects Logistics, member to the Cargo Equipment Experts (CEE) network in Russia, announced about their involvement in a running project to build a temporary oil terminal in Murmansk, Russia
The job of the Beluga Projects Logistics experts is to install on the Kola Bay sea bottom an anchor system of twelve anchor lines, consisting of three anchors with a weight of each 50, 200 and 220 tons. Overall there will be installed and connected 36 anchors in the maximum water depth of 155 meters.
Beluga Projects Logistic carrying now this project with their own equipment and with the following scope of work: